What clients say about working with Bumi Chambers.
Feedback from contractors, developers, and sub-contractors across Klang Valley construction projects.
Back to Home8+
YEARS PRACTICE
120+
CLIENTS ADVISED
4.8/5
CLIENT RATING
45+
CIPAA PROCEEDINGS
Client testimonials
"We engaged Bumi Chambers to handle a CIPAA payment claim that had been stuck for months. The timetable they shared at the start was followed precisely. The adjudication response was comprehensive and the decision went in our favour. What I noticed most was that the counsel who took instructions was also the one who prepared the submission and attended the hearing — there was no handover mid-matter."
Ahmad Hafizi Zainal
Project Director · Petaling Jaya
March 2025
"The pre-award contract review was straightforward — we sent the PAM 2018 document set and received a written risk summary within five working days, well within our procurement window. The note flagged three provisions our commercial team had not picked up. One was renegotiated before we signed. The fee was fixed and exactly as quoted."
Lee Hui Shan
Commercial Manager · Kuala Lumpur
February 2025
"As a sub-contractor, using CIPAA was new territory. Bumi Chambers walked us through the process before we committed, which helped us make a better-informed decision. The briefing note on the Act was genuinely useful. The proceeding was handled efficiently. I would have preferred slightly more frequent updates during the submission stage, but the outcome was the right one."
Rajan Kumar
Managing Director · Subang Jaya
January 2025
"We used Bumi Chambers for a FIDIC subcontract novation involving four parties on a mixed-use Bukit Bintang project. The drafting was precise and worked around our developer's sign-off schedule. The counsel clearly knew the FIDIC novation mechanics — no time was lost explaining the instrument. Fixed fee made budget approval straightforward."
Tan Swee Lian
Development Manager · Kuala Lumpur
March 2025
"The merits note Bumi Chambers produced before we committed to arbitration was the most useful single document in the whole process. It told us what the contemporaneous record supported, where the gaps were, and the realistic range of outcomes. We decided to proceed on the basis of that note, and the outcome was within the range they had described."
Norizah Mat Yassin
Contracts Manager · Shah Alam
April 2025
"We instructed Bumi Chambers to defend a CIPAA claim we believed was substantially overstated. The payment response and adjudication response were clearly structured — the adjudicator's decision reduced the claimed sum significantly. The counsel's familiarity with the AIAC adjudicator's approach was evident in how the submission was put together. We will be returning for our next contract review."
Patrick Koh Wei Boon
Quantity Surveyor · Cyberjaya
February 2025
Selected matter outcomes
Client details generalised and identifying particulars removed.
CHALLENGE
M&E sub-contractor unpaid on three progress claims over five months. Nil payment response from main contractor. Claimed: RM 1.1 million.
SOLUTION
Adjudication claim with full valuation evidence and programme references. Submission addressed belated defects set-off. Oral hearing attended.
RESULT
Decision for substantially the full claimed sum. Payment received within two weeks without enforcement proceedings.
4 months from instructions to decision
CHALLENGE
Developer tendering RM 38 million design-and-build contract on modified FIDIC Yellow Book. Concerns about LD regime and defects provisions.
SOLUTION
Full review in five working days. Risk summary flagged LD regime as disproportionate and an ambiguity in defects notification period. Negotiation positions drafted in writing.
RESULT
Contractor accepted revised terms. Client signed on improved conditions within the original procurement window. Fixed fee, no overrun.
5 working days for full review
CHALLENGE
Main contractor facing RM 3.2 million LD deduction after 14-week overrun. Contractor's position: majority caused by employer VOs and late nominee sub-contractor handovers.
SOLUTION
Programme analysis reviewed in-house. Merits note identified strong position on 8 of 14 weeks. AIAC arbitration claim with programme expert evidence submitted.
RESULT
Award reduced LD to ~35% of original sum. Prolongation costs partially awarded. Costs settled before quantum hearing.
11 months from instructions to award
Reach us directly
TELEPHONE
+60 3-6419 7852ADDRESS
41, Jalan Tun H.S. Lee
50000 Kuala Lumpur
HOURS
Mon–Fri: 9:00am–6:00pm
Sat: By appointment
Considering an instruction?
A matter outline form on the homepage takes less than five minutes to complete. We respond within one working day.
Send a Matter Outline